Learn more about our comprehensive legal services.
Advising our clients on different opportunities and challenges of the industry.
Developing a unique culture, which blends traditional client care with modern technology and working practices since 1851.
Stay up to date on the latest news and legal insights.
News & Insights
Authored by: Joseph Chung
In Steve Ward Services (UK) Ltd v Davies & Davies Associates Ltd [2022] EWCA Civ 153, England’s Court of Appeal unanimously upheld the decision of the court below which had granted summary judgment to an adjudicator to enforce payment of his fees arising from an adjudication in which the adjudicator resigned prior to issuing a decision. The principal issue raised in the appeal concerned an adjudicator’s entitlement to his or her fees, in circumstances where they have resigned from the referral because they did not consider that they had the necessary jurisdiction to decide the dispute. As the Court of Appeal pointed out, there is very limited authority on this point, and it had been eight years since the Court of Appeal last considered an adjudicator’s entitlement to fees in circumstances where the referral did not go as anticipated. The decision is therefore of some importance.
Background
The Defendant (Steve Ward Services (UK) Ltd) carried out construction operations at a restaurant called “Funky Brownz”, owned and operated by a company, BIL as “Funky Brownz”. Ms Vaishali Patel was a director and the majority shareholder in BIL. A set of contract documents were drawn up but not signed, in which the client was described as “Vaishali Patel Funky Brownz”. Invoices for the works as they progressed were addressed to and paid by BIL. As at completion of the works, the Defendant claimed an unpaid balance of £35,974.29 and the parties then fell into dispute on the unpaid balance and defects.
Subsequently, the Defendant commenced adjudication proceedings and appointed Mr Davies of Davies & Davies Associates Ltd as the adjudicator. However, before making a decision, the adjudicator resigned on the basis that BIL was not a party to the adjudication for which he had been appointed and that the relevant contract was in fact between the Defendant and Ms Vaishali Patel.
The adjudicator’s contract of appointment, was made up of i) his letter to the parties; ii) his own terms of appointment; iii) the CIC Low Value Dispute Model Adjudication Procedure (1st Edition)(MAP); and iv) the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998 649), as amended (Scheme).
The adjudicator issued an invoice for payment of his fees, which the Defendant refused to pay, on the basis that the adjudicator had committed a repudiatory breach of his contract of appointment. The Defendant was said to have accepted the adjudicator’s repudiation, so that his terms and conditions of appointment had ceased to have effect.
The adjudicator’s terms and conditions of appointment provided that “In the event of the Adjudication ceasing for any reason whatsoever prior to a Decision being reached, a Fee Invoice will be raised immediately and is due for payment 7 days after the date of the Invoice”. They also provided that “The Parties agree jointly and severally to pay the Adjudicator’s fees and expenses as set out in this Schedule. Save for any act of bad faith by the Adjudicator, the Adjudicator shall also be entitled to payment of his fees and expenses in the event that the Decision is not delivered and/or proves unenforceable.…” (Clause 1).
Decision of the High Court (Technology and Construction Court (TCC))
The TCC held that:
The Appeal
The Defendant appealed against the TCC decision and the adjudicator cross-appealed to challenge the one finding made against him, namely that his reasons for resignation were “erroneous” and that, in so acting, he went beyond his powers.
Issues on appeal
Was there a jurisdictional issue in the adjudication?
The Court of Appeal held that there was.
Was the adjudicator entitled to decline jurisdiction and resign in consequence?
The Court of Appeal held that the adjudicator was entitled to decline jurisdiction and resign because:
Subject to bad faith, was the adjudicator entitled to be paid for the work done prior to his resignation?
The TCC judge had construed the adjudicator’s terms and conditions to mean that he was entitled to be paid fees for the work he had done, unless there had been an act of bad faith on his part. The Court of Appeal held that, subject to the question of bad faith, the judge’s construction of Clause 1 was correct.
The Court of Appeal noted that there was no binding authority on an adjudicator’s entitlement to fees when he or she resigns and that the leading case on an adjudicator’s entitlement to fees when the adjudication does not go as expected is PC Harrington Contractors Ltd v Systech International Ltd [2012] EWCA Civ 1371.
Drawing the various strands together, the Court of Appeal summarised the applicable principles as follows:
Was the adjudicator guilty of bad faith?
The Court of Appeal said that it was made plain in a recent Supreme Court decision that, depending on the circumstances of the case, an act of bad faith will usually require some measure of dishonesty or unconscionability.
The Court of Appeal said that as a matter of principle there was plainly a difference between default or misconduct (an expression used in the Scheme), on the one hand, and bad faith (as per Clause 1 in the adjudicator’s terms) on the other. For the purposes of Clause 1, a finding of bad faith must involve some form of unconscionable or deliberately unacceptable conduct on the adjudicator’s part, which is more serious than simple default. An adjudicator may be guilty of default or misconduct because, as in PC Harrington, he conducts the adjudication in such a way that the parties end up with an unenforceable decision. But that default or misconduct may have been wholly inadvertent on his part.
The Court of Appeal added that the qualitative difference between the two is also reflected in the Scheme. There, liability for the adjudicator’s acts or omissions is excluded, unless there is also bad faith. That makes it plain that bad faith is more serious than simple default or misconduct, and therefore there is a higher threshold before it can be established.
The Court of Appeal held that the adjudicator was not guilty of default/misconduct, much less bad faith. He had raised a real issue as to jurisdiction; he had not received what he quite reasonably considered proper answers; and in the circumstances, in the judge’s words, he had acted with ‘diligence and honesty’ in coming to the conclusion that the proper course was for him to resign.
The only criticism of the adjudicator’s conduct which the Court of Appeal accepted was his failure to give the parties a final warning prior to resigning. However, given the circumstances of this case, that conduct did not fall outside the commercial norms to be expected of an adjudicator. There was nothing unconscionable about what the adjudicator did. He had done his best to get answers to his questions and had failed. Although he should have given the parties one final warning prior to resigning, his failure to do so could not, the Court of Appeal said, by any stretch of the imagination, be described as “bad faith”.
Was Clause 1 contrary to UCTA?
The Court of Appeal held that UCTA had no application in this case.
Adjudicator’s cross appeal
The Court of Appeal allowed the adjudicator’s cross appeal, holding that he did not go outside the ambit of the Scheme and his reasons for resigning were not erroneous.
Discussion
Whilst and to a significant extent, the Court of Appeal’s decision turned on the terms of the Scheme and the adjudicator’s terms of appointment, the key take-aways from this case are (1) whilst adjudication is a fast moving procedure, the parties should nevertheless go through the adjudicator’s terms of appointment carefully before accepting the terms and appointing the adjudicator, and (2) like arbitrations, it is not uncommon in adjudications for there to be questions as to which are the relevant contracting parties. As this case illustrates, the adjudicator should take the initiative and invite the parties to address this issue even if the parties have not raised this as a relevant dispute. If the matter cannot be resolved and the adjudicator has in mind resigning (and depending on the terms of his appointment), he should give a final warning to the parties prior resigning.
Subscribe to Publications
Sign up for our regular updates covering the latest legal developments, regulations and case law.
Media Contact
For media enquiries please contact us at media.relations@deacons.com.
Tel: +852 2825 9211