资讯洞见
In the recent case of MillChris Developments Ltd v Fiona Selski Waters [2020] 4 WLUK 45, before England’s Technology and Construction Court, a party to an adjudication applied for an injunction to prohibit the adjudication continuing on the grounds that due to COVID-19 it had insufficient time to comply with the adjudicator’s directions and would be unable to attend a site visit. The Court declined to make the injunction and ordered that the adjudication proceed. It said that the Court will only very rarely grant an injunction in respect of an ongoing adjudication and only in very clear-cut cases. The Court decided that the threshold for granting an injunction had not been met as the Contractor, MillChris, had not shown that COVID-19 and the fact it was no longer trading prevented it from preparing for the adjudication such that proceeding with it would be in breach of the rules of natural justice. The Court also commented that parties to an adjudication had no right to be present at a site visit and that the adjudicator could therefore conduct the site visit on his own or arrangements could be made for the site visit to be recorded for MillChris or for it to list specific matters for the adjudicator’s attention beforehand.
Background
A home owner (Waters) engaged a contractor (MillChris) to carry out works at her property under a standard form JCT Homeowner Contract, which included a provision for adjudication. The works commenced in September 2017 and in November 2019 MillChris ceased trading. On 23 March 2020 Waters commenced an adjudication, alleging defective works and also that she had been overcharged by £45,000.
Adjudication
An adjudicator was appointed who directed that a response be served by 3 April 2020 and a site visit take place on 14 April 2020. On 26 March, MillChris’s solicitor wrote to the adjudicator stating that it was not possible to comply with the deadline due to the COVID-19 situation and that the adjudication proceedings should be postponed until the COVID-19 lockdown was lifted. Although the adjudicator recognised the difficulties posed by COVID-19, he decided that the adjudication should proceed and proposed a two-week extension to the timetable. MillChris did not agree to that extension, asserting that it could take several months to get the COVID-19 situation under control. MillChris submitted that if the adjudication went ahead, it would be conducted in breach of the rules of natural justice because it had insufficient time to prepare for it as a result of COVID-19 and the fact that it was no longer trading. MillChris said that its solicitor had been forced to self-isolate at home, which had made it difficult to obtain evidence from those with knowledge of the dispute, and that it would be unfair to proceed with the site visit where none of its representatives were able to attend and there was insufficient time to appoint an independent surveyor to be present.
Injunction Application
MillChris applied for a prohibitory injunction prohibiting Waters from continuing with the adjudication. It also sought a mandatory injunction that Waters withdraw the reference to adjudication. It was accepted that the Court had jurisdiction to grant an injunction which would inhibit or stop the progress of an adjudication.
Court’s Ruling
The Court declined to grant the injunction and ordered that the adjudication should proceed. It held:
Comments
This is the first case brought to our attention arising out of Covid-19. Whilst adjudication is not common in Hong Kong, similar objections may be raised in arbitration during the lockdown and how the Hong Kong Court will deal with such has yet to be seen.