Learn more about our comprehensive legal services.
Advising our clients on different opportunities and challenges of the industry.
Developing a unique culture, which blends traditional client care with modern technology and working practices since 1851.
Stay up to date on the latest news and legal insights.
News & Insights
Authored by: Stanley Lo
In WRB (N.I.) Ltd v Henry Construction Projects Ltd [2023] EWHC 278 (TCC), the Claimant sought summary judgment to enforce an adjudicator’s decision in its favour, while the Defendant sought a stay of execution of enforcement. The judgment usefully sets out the legal principles applicable to such stay applications. In this case, the court refused to grant a stay.
Background
The action concerned a dispute arising out of a construction project in relation to which Henry Construction Projects Ltd (HCPL) was the main contractor. HCPL engaged WRB (N.I.) Ltd (WRB) to design, supply, install, test and commission the mechanical, electrical and public health systems for the project for a total of £2.18 million plus VAT. The unusual feature in this case was that WRB was a dormant company prior to the Sub-Contract and remained such. WRB in a previous adjudication disputed that it was a party to the Sub-Contract, arguing that the true sub-contractor under the Sub-Contract was WRB Energy Ltd, while HCPL contended that it had contracted with WRB. The previous adjudicator ruled that WRB was the true sub-contractor.
Adjudication
WRB served a notice of adjudication in respect of the value of an interim payment application and the adjudicator decided that the true balance owed to WRB was £120,655.35 plus interest of £96.79 to 13 May 2022. The adjudicator directed HCPL to pay £120,752.14 including the interest payable to 13 May 2022 and thereafter interest until payment at the daily rate of 99p. HCPL made no payments pursuant to the adjudicator’s decision. WRB subsequently applied to court for summary judgment to enforce the adjudicator’s decision. HCPL applied to stay enforcement pending adjudication of its asserted cross claims. It also argued that WRB’s parlous financial standing meant that it was highly probable that any monies paid now would not be repaid in the event that HCPL should succeed in its own claim.
Legal Principles
The court referred to the legal principles applicable to applications to stay enforcement of adjudicator decisions, as follows:
Court’s Decision
The court concluded that this was a case where it was probable that, should the court refuse a stay and HCPL later established its own cross-claim, WRB would be unable to repay the judgment sum. While such risk could be addressed, or at least mitigated, by the guarantee offered by WRB Energy Ltd, HCPL had not established that it would be inexpedient to enforce the adjudicator’s decision because:
(i) On its own case, HCPL chose to place the Sub-Contract with a newly formed dormant company. The risk it now complained of was the inevitable consequence of having placed this Sub-Contract with a dormant company. It was the result for which it contracted. It would be unfair and contrary to the spirit of the adjudication regime to allow HCPL to now escape its liability to meet an adjudication award on the basis of WRB’s essentially unchanged financial position.
(ii) It was HCPL that resisted the argument that the true sub-contractor was WRB Energy Ltd. It had essentially made its own bed.
(iii) This judgment became regrettably delayed behind a judgment in another very substantial TCC case. By the time it is handed down, HCPL will have had ample opportunity to establish its alleged entitlement upon its cross-claims.
Accordingly, the court did not require WRB Energy Ltd to provide a guarantee and it dismissed the application for a stay.
Comments
This case, like J&B Hopkins Ltd v A&V Building Solution Ltd reported in this Newsletter, illustrates that it is difficult to resist enforcement of an adjudicator’s decision and respects the principle of using adjudication as a quick and inexpensive method of temporarily resolving disputes in construction contracts.
Subscribe to Publications
Sign up for our regular updates covering the latest legal developments, regulations and case law.