Learn more about our comprehensive legal services.
Advising our clients on different opportunities and challenges of the industry.
Developing a unique culture, which blends traditional client care with modern technology and working practices since 1851.
Stay up to date on the latest news and legal insights.
News & Insights
In Saga Cruises BDF Limited v Fincantieri SPA [2016] EWHC 1875, the English High Court held that two delays which occurred within the same time period are not necessarily “concurrent” in the legal sense of the word. One must bear in mind the orthodox rules of causation to determine whether each delay had an actual impact on the completion date.
Background
In 2010, Saga Shipping (Owners) purchased a cruise ship and engaged Fincantieri, an Italian shipbuilding company (Contractor), to refurbish the ship for €14.3 million.
The contract contained a clause imposing liquidated damages on the Contractor for delay in completing the works by the Scheduled Completion Dateas follows:-
“Amount of liquidated damages. If the completion of the Works is delayed beyond 23.59 GMT on the Scheduled Completion Date (as adjusted pursuant to this Agreement) for any reason whatsoever for which the Contractor is, or its employees, agents or sub-contractors are, responsible, the Contractor shall pay to the Owner liquidated damages …”
Liquidated damages were capped at €770,000.
The works were scheduled to be completed by an extended Scheduled Completion Date of 2 March 2012. The Contractor did not achieve Completion until 16 March 2012. The Owners claimed €770,000 in liquidated damages for the Contractor’s delay between the extended Scheduled Completion Date (2 March 2012) and Completion (16 March 2012).
The Court found that:-
Was there concurrent delay?
One of the main issues before the court was whether any or all periods of delay for which the Contractor was found responsible were also the fault of the Owners and therefore concurrently caused.
The Arguments
The Contractor argued that where completion is delayed by two events concurrently, one for which the Contractor was responsible and the other for which the Owners were responsible (as in this case), no liability for liquidated damages arose, as the Contractors were entitled to an extension of time for the period of delay not accountable to them, notwithstanding the concurrent effect of the other event.
The Owners argued that the delays were not concurrent. They argued that if completion was already delayed for reasons for which the Contractor was responsible, then delays for which the Owners were responsible were not examples of concurrent delay and did not give rise to any entitlement to an extension of time by the Contractor because they did not in fact cause any delay to completion.
The Court’s Decision
The Court reviewed a long line of cases on the topic of concurrent delays and concluded that the most useful synthesis of the issue of concurrent delay in the context of extensions of time is the analysis of Hamblen J (as he then was) in Adyard[1], namely :-
The Court concluded that unless there is a concurrency actually affecting the completion date as then scheduled, the contractor cannot claim the benefit of it. Causation must in fact be proved based on the situation at the time as regards delay.
The Contractor was responsible for a number of delays beyond the extended Scheduled Completion Date and was not entitled to rely on the delays for which the Owners were responsible during that period as stopping time running under the liquidated damages clause. Delays caused by the Contractor had effect between 2 March 2012 and 16 March 2012 and delays caused by the Owners had effect up to 14 March 2012. It was clear, the Court said, that the Owner’s delays did not actually impact the completion date, because their effects ended on 14 March i.e. before 16 March. Hence, the Owner’s delays could not be said to be concurrent to the Contractor’s delays and thus the Contractor was not entitled to an extension of time and the Owners were entitled to €770,000 by way of liquidated damages.
Comment
In a construction project, whether the contractor is entitled to an extension of time for completion of the works is determined by the precise wording of the terms of the contract. Where there are two sets of delays, one caused by the employer and one by the contractor, one must carefully examine the actual impact of each set of delays on the project completion date. Two delays are only concurrent when they are of approximately equal causative potency, and when each delay has actually caused delay to the completion date. The conclusion reached by the English Court in this case is consistent with the Guidance published by the English Society of Construction Law Delay and Disruption Protocol (2nd Edition).
[1] Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm)
Subscribe to Publications
Sign up for our regular updates covering the latest legal developments, regulations and case law.
Media Contact
For media enquiries please contact us at media.relations@deacons.com.
Tel: +852 2825 9211