Learn more about our comprehensive legal services.
Advising our clients on different opportunities and challenges of the industry.
Developing a unique culture, which blends traditional client care with modern technology and working practices since 1851.
Stay up to date on the latest news and legal insights.
News & Insights
Concurrent delay is an issue featuring in many construction disputes where responsibility for delay in completion of the project is in issue between the parties. It can mean one of the following situations when there is more than one event said to have caused the delay:-
Concurrent delay was argued in the case City Inn Ltd v Shepherd Construction Ltd (2010), which was before the Inner House of the Scottish Court of Session (Scotland's court of final appeal). The case concerned how the architect should grant an extension of time when there was concurrent delay. The relevant condition ("the Condition") in the contract dealing with delay in the progress of the works allowed the architect to give an extension of time if the reason for the delay was a "relevant event" (as defined in the contract), and one of the definitions being the late issue of instructions. Lord Osborne gave the majority decision and formulated certain propositions (based on his review of case law) as regards the proper approach to be taken to the application of the relevant Condition in the contract, as follows:-
These findings are not entirely consistent with the conventional approach in previous cases decided by the English Courts. It appears from many English authorities that where two or more events are causes of the same delay, the contractor is entitled to an extension of time provided that one of the events is a relevant event. We are not aware of any case where apportionment of the delay has been accepted by the Courts.
Whilst many contractors and employers may find the above findings useful in arguing extension of time in cases of concurrent delay, the prevailing view is that it is unlikely to be followed in England. In the recent English High Court case of Adyard Abu Dhabi v SD Marine Services (2011). Hamblen J. expressly held that the English approach in the situation referred to in (v) above would be to recognise that the contractor is entitled to an extension of time and not an apportionment. This case involved ship building, but the principles referred to in relation to assessing extensions of time should be equally applicable to construction cases.
Although the City Inn decision is binding in Scotland, it is only persuasive in England and other jurisdictions, where it seems that construction lawyers are still free to raise various arguments in respect of concurrent delay.
Subscribe to Publications
Sign up for our regular updates covering the latest legal developments, regulations and case law.